 Pembangunan Proyek JIS Capai 28,64 persen

JIS Project Work Has Reached 28.64 Percent

The Jakarta International Stadium (JIS) construction, Tanjung Priok, North Jakarta is still undergoing. It has touched 28.64 percent and the deviation reaches -2.52 percent.

We're also working on the training field area and erecting the west ramp of the BMW park

Arnold Kindangen, Corporate Communication & Commercial for JIS Project said, from the value of realization progress based on the calculation of the Operational Cooperation (KSO), the project plan was to reach 31.16 percent.

"Deviation is -2.52 percent due to constraints in the material import process related to the import restriction policy from the government to empower local products. The project requires imported steel materials from China for the construction of a roof that can be opened and closed as much as 5,000 tons, but now only 200 tons," he expressed, Friday (10/2).

PAM Jaya to Supply JIS's Clean Water Next Year

He stated, for shortages of steel roof construction materials were still in process and scheduled in this week was already on the way. As for the synthetic grass used was Limonta Mixto from Italy, which was currently in Tanjung Priok Port.

To speed up the project work, his party would optimize works that could be advanced such as working on training fields. While the construction that was currently underway included the 1st, 2nd, 3rd, 4th, 5th, 6th and 7th floor construction.

"We're also working on the training field area and erecting the west ramp of the BMW park," he stated.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1932 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1023 personDessy Suciati
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye718 personBudhi Firmansyah Surapati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye637 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye496 personDessy Suciati